Board test and program work is most easily done in panel arrangements, where GND and 3V3 are connected once on a rail edge.
Steps to reproduce
Refer to the panel layout
Examine the rail edges
Search for power connectors
Expected result
A general GND and 3V3 connection is available in the panel.
Actual result
No power connection is possible on panel structures.
Severity level
This is low priority because boards can be tested and programmed individually.
# Power circuits are missing from panel
## Problem environment
Board test and program work is most easily done in panel arrangements, where GND and 3V3 are connected once on a rail edge.
## Steps to reproduce
1. Refer to the panel layout
1. Examine the rail edges
1. Search for power connectors
## Expected result
A general GND and 3V3 connection is available in the panel.
## Actual result
No power connection is possible on panel structures.
## Severity level
This is **low priority** because boards can be tested and programmed individually.
Michael Schloh von Bennewitz
ha añadido esto al hito Postproject catchallhace 4 años '
issues.change_milestone_at=`modificó el hito de %!s(MISSING) a %!s(MISSING) %!s(MISSING)
Power circuits are missing from panel
Problem environment
Board test and program work is most easily done in panel arrangements, where GND and 3V3 are connected once on a rail edge.
Steps to reproduce
Expected result
A general GND and 3V3 connection is available in the panel.
Actual result
No power connection is possible on panel structures.
Severity level
This is low priority because boards can be tested and programmed individually.
Solved in 5dd172c, but please remember to adjust new panel frames accordingly!